As reported by the Wrocław branch of GDDKiA:

We are continuously carrying out work related to expanding the transport system across the Bóbr River in Bolesławiec along national road No. 94. As part of the investment, two new bridges will be built: the northern bridge at a new location next to the existing structure, and the southern bridge on the site of the existing one, which will be demolished and replaced with a new structure.

What work is currently under way?

The road administrator:

Work is currently under way on the construction of a new bridge over the Bóbr River in Bolesławiec. The contractor is carrying out work on formwork construction and the installation of reinforcement. The new structure will be a three-span, two-girder prestressed-concrete bridge measuring 115 m in length.

And adds: – Construction of the northern carriageway involves using 1,250 cu m of concrete mix, 260 tonnes of steel, as well as 36 tonnes of prestressing steel.

More information about this investment can be found in the article Two twin bridges and turbo roundabouts will be built in Bolesławiec. The road administrator provides details about the investment.

Bolesławiec on our cameras: