Construction work will continue until the end of May 2025. The project will include a modern water supply network measuring 153.3 linear metres, as well as branches for hydrants with a total length of 4.2 linear metres.

Additionally, a sewage network measuring 747.2 linear metres will be built.

The parties involved in the project are: investor – the Municipality of Bolesławiec, contractor – JAGIELSKI from Bolesławice near Bolesławiec, and investor supervision – Przedsiębiorstwo Wodociągów i Kanalizacji Dolina Bobru from Bolesławiec.

The contract for the construction work is worth PLN 734,444. The project is being carried out under the “design and build” formula, which allows for more effective management of the construction work.

The completion of the water and sewage network construction will contribute to the further development of the Przylesie housing estate in Bolesławiec.