City Hall:

Bolesławiec Mayor Piotr Roman informs that the websites of the General Directorate for National Roads and Motorways contain information about the opening of bids for the task “Expansion of the transport system, including the reconstruction of the existing bridge and construction of a new bridge over the Bóbr River along national road no. 94 (formerly no. 4) in Bolesławiec”.

ListaLista • Photo author: UM Bolesławiec

Bolesławiec officials sum up:

A total of 11 bids were submitted, and 10 of the 11 bids fall within the budget of the General Directorate for National Roads and Motorways. The lowest bid, submitted by Himmel i Papesch Opole Sp. z o.o., amounts to PLN 40 876 086.87. The highest, amounting to PLN 62 186 027.08, was submitted by ALUSTA S.A.

The GDDKiA budget for carrying out this task amounts to PLN 55 595 396.00.

And they add: – GDDKiA will now analyze the bids. The contractor selected through the tender will be responsible for completing the project within 32 months of signing the contract.

We will certainly return to this subject.