The investment will be carried out in two stages. City officials: – The first stage includes the construction of 219 metres of road. Work related to the first stage will be completed by 31 March 2024.

The second stage includes the construction of more than 200 m of road. Completion of the work: the end of July 2024 .

Officials list the following:

  • The scope of work near Kresów II RP Street includes the construction of a stormwater drainage system and retention basin, as well as the installation of street lighting.
  • The planned work includes:
    • an asphalt-concrete roadway,
    • a pedestrian and cycle path,
    • topsoiling of adjacent areas along with grass seeding,
    • the installation of horizontal and vertical road markings.

The value of the work is PLN 2 790 000. The funds come from the Bolesławiec city budget.