The 255-metre-long, worn section of the shared pedestrian and cycle path in the woodland along Jeleniogórska Street—up to the pedestrian crossing near Leśny Potok—was modernized.

City Hall: – The work involved constructing a surface using native soil, including crushed basalt aggregate. On the woodland section, a wooden edging made of black locust was installed.

Importantly, the work was carried out in consultation with the Bolesławiec Forest District and Bolesławiec County.

Contractor: Miejski Zakład Gospodarki Komunalnej w Bolesławcu. Cost: PLN 159,777. Funding: from the budget of the City of Bolesławiec. All of this was carried out as part of the project “Developing a concept for connecting existing cycle paths and constructing them,” using the existing natural potential and scenic and tourist assets.