As the city authorities report: – Work on the construction of the road along Nadrzeczna Street is nearing completion. The first stage of the investment involves building a 155-metre section connecting Dolnych Młynów Street with Mostowa Street.

What has been done?

  • A 3-metre-wide pedestrian and cycle path with a red asphalt surface has been built along the road.
  • As part of the investment, a raised intersection has been built.
  • A shoulder reinforced with concrete paving blocks and drainage have been installed.

The contractor is the company Świadczenie Usług Transportowo-Budowlanych” from Radostów Dolny near Lubań.

The office adds:

It is worth recalling that street lighting was installed along Nadrzeczna Street in previous years. In 2019, 16 street lamps with LED fixtures were installed along Nadrzeczna Street. They can reduce energy consumption to 14W and allow remote control and monitoring of the circuit. An air pollution meter was also placed on one of the poles. Through the Airly app, it enables residents to check the current level of air pollution.