The value of the works is PLN 356,700. The funds come from the Bolesławiec city budget. The dismantling of the old surfaces is currently underway.
The project includes the construction of parking spaces, pavements, a maneuvering road and lawns. The surfaces of the maneuvering road, parking spaces and pavements will be made of concrete paving blocks, covering a total area of 1,182.65 sq m.
The work also includes park-style street lighting (4 units) with LED light sources and drainage of part of the area by the building numbered 7 to 11, connected to the combined sewer system.
The work will continue until mid-October this year.