On 16 October, officials approved the quality of the work carried out to build the roadways and pavements on Rumianków and Tulipanowa streets—from the section between Różana Street and Ptasia Street. A road over 180 m long was built on Rumianków Street, and one over 108 m long on Tulipanowa Street. Pavements made of concrete paving blocks and driveways to properties were installed on both sides of the roadway.
As part of the work, drainage and street lighting were installed. The road on Tulipanowa and Rumianków streets is lit by 11 street lamps. The investment was carried out by a company from Świdnica. Its cost was over PLN 467,000. The construction was financed from the budget of the city of Bolesławiec.
(UM/ii information)