After the opening of the new bridge over the Bóbr and the transfer of road traffic onto it, the contractor began the next stage of the reconstruction of DK94 in Bolesławiec. The old crossing was closed to traffic, and its demolition began. The asphalt has already been removed, and the subsequent stages of demolishing the existing crossing will begin shortly.

The reconstruction will also include the road layout on both sides of the river. Turbo roundabouts are planned at the ends of the bridges; they are intended to increase the capacity of the intersections and improve traffic flow. A new roundabout will also be built near Widok Street, while the existing roundabout at Zgorzelecka Street will be reconstructed.

The changes will also cover the intersections of DK94 with Spacerowa Street and the municipal road. The investment will also include new pavements and cycle paths, bus bays, stormwater drainage, lighting, and solutions improving safety.

LIVE camera at the bridge:

The entire project includes the reconstruction of approximately 600 metres of DK94. Once the investment is completed, Bolesławiec will have two new bridges and a completely reconstructed transport network in the area of the Bóbr River.

According to information from GDDKiA, all works are scheduled to be completed in the second half of 2027.