The Wrocław branch of the General Directorate for National Roads and Motorways has just announced that a tender has been issued for renovation of the concrete surface of the A4 motorway on the Krzyżowa–Krzywa section:
Bids will be accepted until April 13 this year.
What work will be carried out there?
The contractor’s task will be to design and carry out the renovation or replacement of damaged concrete slabs on the A4 motorway section between the Krzyżowa and Krzywa interchanges.
The work will include, among other things, dismantling the existing surface where concrete slabs have cracked, renovating and replacing the surface, repairing the subbase, and restoring drainage elements.
That is not all. Road workers say: – In addition, the shoulders will be repaired and the road markings will be restored.
How long will it take?
The selected contractor will have a total of 65 days from the date the contract is signed to complete the task. The authority reassures drivers: – However, the work itself and the resulting disruptions will last no longer than 20 days.