A new 136-metre section of asphalt road has been built, along with 14 parking spaces (including one for people with disabilities), made of eco-friendly openwork paving slabs.

Drainage and safety have also been improved – drainage channels were constructed, inspection chambers, inlets and a new stormwater sewer system were installed. In addition, five LED streetlights were put up, providing better illumination after dark.

The work was carried out by Meliobud from Nowogrodziec. The investment cost PLN 599,000 and was fully financed from the budget of the City of Bolesławiec.

Wyremontowany łącznik ulicy Orlej i ZgorzeleckiejWyremontowany łącznik ulicy Orlej i Zgorzeleckiej • Photo author: istotne.pl