As established by the lwowecki.info website, Tauron Ekoenergia has selected the contractor for the “EW Pilchowice I Modernization of Water Reservoir Facilities” investment:

The contract (...) will be carried out by a company from Kiełczów, which submitted a gross bid of PLN 114,456,184.32 for the basic scope, and PLN 53,397,635.43 for the optional scope. Interestingly, the contracting authority rejected the bids submitted by the two other bidders.

When will the work begin?

The contractor should enter the construction site within three months. The Lwówek newspaper reports: – However, the contract completion deadline provides for the investment to be carried out within 24 months of the date on which the construction site is handed over, meaning that by March 2028, the Pilchowice Dam should already be ready for acceptance.