The project includes a range of works, including the construction of a municipal road 5 metres wide, an internal road with similar parameters, an intersection with Bronisława Kosiby Street, and road lighting. With pedestrian and cyclist safety in mind, a pedestrian and cycle path will be built along the road, as well as pedestrian crossings with bicycle crossings. Another important element of the project is the construction of a retention basin and a stormwater drainage system, which will enable effective management of rainwater.

The construction of the road at Generała Tadeusza Rozwadowskiego Street is being carried out by ELTOR from Lubań, and the works are scheduled for completion by the end of October 2025. This investment will certainly bring many benefits, including significant improvements in transport.

Będzie nowa droga na Koziej GórceBędzie nowa droga na Koziej Górce • Photo author: Miasto Bolesławiec

The total cost of the investment at Generała Tadeusza Rozwadowskiego Street is PLN 2,290,000. It is co-financed by the Government Polish Deal Fund: Strategic Investment Programme, under the project entitled “Construction of municipal roads – connecting residential and service areas in Bolesławiec.” The programme provides funding for the construction of three roads in Bolesławiec: Generała Tadeusza Rozwadowskiego Street, Generała Józefa Hallera Street, and Sokola Street. The co-financing for the construction of these roads amounts to PLN 8,000,000, representing 91.43% of the final investment value.

MapaMapa • Photo author: UM Bolesławiec