This concerns the Krzyżowa–Krzywa section of the A4 and the area around the Wądroże Wielkie interchange. As reported by the rynekinfrastruktury.pl service:
One bid was submitted in response to the tender announced by GDDKiA. It was submitted by SAT from Oława. The work was priced at PLN 2.132 million. This amount is within the budget prepared by the contracting authority, which had planned to spend PLN 2.736 million.
What will be done?
Portal:
The contractor's task will be to design and carry out repairs and stabilize the concrete surface of the northern carriageway of the A4 motorway at several locations along the Krzyżowa–Krzywa section. New pavement will be installed where the slabs are cracked.
The aim? To make it safer there. The company from Oława will have 45 days to complete the task.