The Mayor of Nowogrodziec Robert Relich successfully accepted the construction works related to the construction of a road in the Special Zone for Small Enterprises in Wykroty.
As we read on the website of the Municipal Office in Nowogrodziec, the main objectives of the project were “improving road safety, better access to and comfort of commuting to workplaces, as well as increasing traffic flow and creating an efficient transport connection.”
What was done?
- A 360-metre-long, 7-metre-wide roadway was constructed.
- Road lighting was installed.
- As part of the construction, an SMA stone mastic asphalt surface was laid along the entire length of the road.
The total cost of the project was PLN 1,365,459.91. Funding from the Polish Deal: PLN 1,140,000.00.