The second stage of the reconstruction of county road No. 2294D from Suszki to Stare Jaroszowice has been completed. As part of the project, a new road structure was built along a section of approximately 1,700 metres (650 metres in the first stage).

Access roads to properties, culverts beneath the access roads and beneath the carriageway were built and reconstructed. New drainage ditches were dug, along with a drainage system. An asphalt pavement was laid along a length of 1,300 metres. The bus bay, together with its shelter, was reconstructed.

The carriageway is now 6 metres wide. It is marked, and energy-absorbing barriers have been installed at critical locations.

The reconstruction cost PLN 3.5 million. The project was completed thanks to the financial participation of Gmina Bolesławiec and Powiat Bolesławiecki.