As part of the project, 57 parking spaces for passenger cars and 3 spaces for people with disabilities will be built, along with a maneuvering roadway.
The parking lot will be connected to the municipal road by an access driveway. The parking lot will be paved with concrete blocks, which allow rainwater to drain directly into the ground through wide joints.
The planned area of the parking lot is 765.6 m², the maneuvering roadway 962.1 m², and the sidewalk 67.3 m². The project is worth PLN 340,000. The contractor is “Eltor” from Lubań. The work is scheduled for completion by the end of May 2020.
The parking lot will be built near the church and sports complex. It is worth recalling that the complex was established in 2015 and consists of a 19.10 × 32.10 m multifunctional field with a polyurethane surface and a 30 × 62 m football field with an artificial-grass surface.
The complex includes an outdoor gym with stainless-steel equipment, chess tables with seats, and three stands. The area is illuminated.