The complex under construction will consist of a multifunctional sports court measuring 19.10 x 32.10 m, with a polyurethane surface, and a football pitch measuring 30 x 62 m, with an artificial grass surface. The complex will also include an outdoor gym with stainless-steel equipment, two chess tables with seats, and three stands with approximately 28 seats each. The cost of constructing the sports complex together with the accompanying infrastructure is PLN 1,544,000. The contractor is Bud-Ziem from Pszenno. The facility will be fenced and illuminated.

Remonty i inwestycje w BolesławcuRemonty i inwestycje w Bolesławcu • Photo author: UM Bolesławiec

The second stage of work on the reconstruction of the road on Obrońców Helu Street in Bolesławiec has been completed. The work covered the reconstruction of the road from the intersection with Komuny Paryskiej Street to Garncarska Street. The work included, among other things:

  • drainage of the road body
  • milling of the existing asphalt surface
  • laying new layers
  • adjustment of water-supply valves and telecommunications and sewer manholes.
Remonty i inwestycje w BolesławcuRemonty i inwestycje w Bolesławcu • Photo author: UM Bolesławiec
Remonty i inwestycje w BolesławcuRemonty i inwestycje w Bolesławcu • Photo author: UM Bolesławiec

A gutter was laid from granite paving stones. It is worth recalling that the pavements on Obrońców Helu Street were renovated in December last year. The lighting was also modernized as part of the work. The work was carried out by Sab-Bud from Bolesławiec. The total cost of reconstructing Obrońców Helu Street amounted to PLN 385,680. The project was co-financed by Bolesławiec County in the amount of PLN 250,000. The contractor for the second stage was Ogrody Jagielski from Bolesławice.

In September, partial repairs to roads and pavements were carried out on streets including Wałowa, Traugutta, Konradowska, Sucharskiego, Piotra Skargi, Dąbka and Narutowicza. Paving stones were replenished on Ekonomiczna, Brody, Łukasiewicza and Bankowa streets. At raised and sunken sections on Piastów Street, the paving stones on the pavement and cycle path were relaid. The entrance to the school on Bankowa Street was renovated. Sunken paving stones around street lamps were relaid on Łukasiewicza Street. Grading of unpaved roads and temporary surfacing were carried out on Powstańców Warszawy Street and on the Gdańska–Warszawska streets, on the access road to garages. The stairs providing access from Cicha Street to the buildings on Parkowa and Zygmunta Augusta streets were renovated.

Road signs were repaired and cleaned on the following streets: Parkowa, Sadowa, Piotra i Pawła, Ekonomiczna, Bankowa, Warszawska, Akacjowa, Królowej Jadwigi, Jana Pawła II, Wańkowicza, Bielska, Zgorzelecka, Chopina, Bankowa, Bielska, Armii Krajowej, Opitza, aleja Tysiąclecia, 10 Marca, Różana, Małachowskiego, Lipowa, Staszica (side street), Matejki and Leśna.

Missing signs were replaced or supplemented on streets including Kutuzowa, Willowa, Kościelna, Gałczyńskiego, Parkowa, Bankowa, Armii Krajowej, Rynek, Braci Śniadeckich, Ceramiczna, the Kwiatowe estate – terminus, Matejki, Bielska and Jezierskiego. A mirror was also installed at 4–6 aleja Tysiąclecia.