Project objectives for 2013:
- construction of more than 15 kilometers of fiber-optic and microduct networks,
- connecting 31 units of the Municipality of Bolesławiec,
- launching infokiosks at 29 units,
- providing 200 households with ready-to-use computer equipment and software,
- training 400 people in computer use, office applications and internet access.
The total project cost is: PLN 7,384,169.00 (2013: PLN 5,307,315.00). EU Operational Programme Innovative Economy funding: PLN 5,910,052.78 (2013: PLN 4,481,605.00). Cost to the Municipality of Bolesławiec: PLN 1,474,116.22 (2013: PLN 825,710.00).
Project schedule:
- construction of the fiber-optic network – completion in July 2013
- launch of the fiber-optic network – July 2013
- delivery of computer equipment – July/August 2013
- beneficiary training – August/September 2013
- computer equipment upgrade – October 2015
What the beneficiary will receive:
- desktop computer
- keyboard, mouse
- monitor
- operating system
- office suite
- internet connection of approximately 2 Mbit/s
- technical support during the project durability period.
(information commissioned)