Today's interruptions (14.08.2026) in electricity supply

Hours Type of outage Location
05:48 - 09:00 (expected completion) ongoing failure IWiny

Planned interruptions in electricity supply (for the next 5 days)

Day Hours Location
18.08.2026 (in 4 days) 08:30 - 10:00 Kraśnik Dolny, numbers 62 to 87A, Dino store, Cieśla building supplies wholesaler – brief interruptions in electricity supply.
18.08.2026 (in 4 days) 08:30 - 13:30 Parowa, numbers 61 to 76, Bronowiec 9, 12.
18.08.2026 (in 4 days) 09:00 - 13:30 Kraśnik Dolny, numbers 88 to 118B.
18.08.2026 (in 4 days) 13:00 - 14:30 Kraśnik Dolny, numbers 62 to 87A, Dino store, Cieśla building supplies wholesaler – brief interruptions in electricity supply.
19.08.2026 (in 5 days) 09:00 - 14:00 Kraśnik Górny, numbers 4C to 4E, 5 to 19A, 76 to 84.

Planned interruptions in electricity supply are an inherent part of work carried out by distribution network operators. They most often result from the need to carry out infrastructure maintenance, modernize power lines, replace worn equipment or connect new customers to the network. A temporary power shutdown allows the necessary work to be performed safely and reduces the risk of failures in the future.

Operators announce planned outages in advance so that residents and businesses can plan their responsibilities accordingly. It is worth following the published schedules regularly, as the scope and duration of interruptions may vary depending on the work being carried out. Thanks to regular modernization, the power network is becoming more reliable, resulting in fewer unplanned failures and greater security of energy supplies.