As reported by the Nowogrodziec Municipality and City Office:

Thanks to the professional organization and commitment of the contractors, residents can now use the new road sections.

And adds:

Details of the completed investments:

Gościszów

Reconstruction of four road sections with a total length of 502 linear metres. The work was carried out by “Świadczenie Usług Transportowo-Budowlanych Stanisława Torba z Radostowa Dolnego”
Cost: PLN 388,975.20 gross.

Gierałtów

Reconstruction of an access road to agricultural land, length: 293 linear metres, width: 3 metres.
Contractor: MARTYN-DROG Sp. z o.o.
Cost: PLN 217,055.34 (including funding from the Dolnośląski Urząd Wojewódzki we Wrocławiu: PLN 117,200.00).

Zagajnik

Reconstruction of Wesoła Street, length: 549 linear metres, width: 3 metres.
Contractor: Przedsiębiorstwo Budownictwa Drogowego Franciszek Michalik
Cost: PLN 354,121.92 (including funding from the Dolnośląski Urząd Wojewódzki we Wrocławiu: PLN 219,600.00).

And sums up: – We thank everyone involved in carrying out these projects! New roads mean not only more comfortable travel, but also support for local development and safety.