Local authorities report: – The completed roads constitute the second part of an investment project involving the construction of a total of nine roads in Gromadka Municipality.
They add:
Scope of the completed road works:
- Construction of an internal road in Krzyżowa (a total of 971 linear metres of roads, 3.5–4.0 m wide, with an asphalt-concrete surface)
- Construction of an internal road in Borówki (351 linear metres of road, 3.0 m wide, with an asphalt-concrete surface, together with a pavement and drainage along the road)
- Construction of an internal road on Leśna Street in Gromadka (290 linear metres of road, 3.0 m wide, with an asphalt-concrete surface, together with a granite-paver pavement)
- Construction of an internal road in Modła to properties no. 2–5 (115 linear metres of road with a concrete-paver surface).
The contractor is the Lubin-based company Masy Polskie. Gromadka Municipality: – As part of the third section of the contract, the remaining works include roads on Ogrodowa Street in Gromadka, together with a pavement along part of the road; in Nowa Kuźnia, together with street lighting; and in Pasternik, together with the construction of a granite-paver parking bay.