As part of the project, 13 significant road projects throughout Bolesławiec County underwent comprehensive modernization and reconstruction.
As part of the undertaking, construction works were carried out as part of the following tasks:
- reconstruction of county road no. 2287D in Lipiany, approximately 915 m long,
- reconstruction of county road no. 2886D between Kraśnik Górny and Szczytnica, approximately 712 m long,
- reconstruction of county road no. 2273D on the Gościszów–Mściszów section, approximately 990 m long,
- reconstruction of county road no. 2496D in Gościszów, approximately 990 m long,
- reconstruction of county road no. 2311D – Gdańska Street in Bolesławiec, approximately 540 m long, together with reconstruction of the sidewalk,
- reconstruction of county road no. 2285D – Gen. Władysław Sikorski Street in Gromadka, approximately 990 m long, together with reconstruction of the sidewalk,
- reconstruction of county road no. 2285D on the Osła–Gromadka section, 990 m long,
- reconstruction of the sidewalk in Zebrzydowa, approximately 520 m long,
- reconstruction of county road no. 2319D – Staszica Street in Bolesławiec, approximately 405 m long, together with reconstruction of the sidewalk,
- reconstruction of Kosiby Street in Bolesławiec, involving construction of a pedestrian and cycling path from Kosiby Street to the intersection with voivodeship road no. 363 in the village of Łaziska, approximately 1,240 m long,
- reconstruction of county road no. 2323D – Staroszkolna Street in Bolesławiec, approximately 272 m long,
- reconstruction of county road no. 2323D – Staroszkolna Street in Bolesławiec, approximately 410 m long, together with construction of a sidewalk,
- reconstruction of the intersection of county roads nos. 2272D and 2287D in Kraśnik Dolny, together with construction of a sidewalk approximately 250 m long and a bus bay.
Thanks to funding obtained from the Government Polish Deal Fund: Strategic Investment Programme, the County’s own funds, and the involvement of local governments and institutions, the stated objectives were successfully achieved.
The acceptance of the completed works took place with the participation of Bolesławiec County Head Tomasz Gabrysiak, Deputy County Head Patryk Hałka, Deputy Mayor of Bolesławiec Robert Rzepnicki, Mayor of Nowogrodziec Joanna Świder, Bolesławiec Municipality Head Andrzej Janiec and Warta Bolesławiecka Municipality Head Mirosław Haniszewski.
The newly renovated and adapted county roads will not only improve the region’s road infrastructure but also positively affect residents’ travel comfort and the economic development of our county.