The new 6-kilometre infrastructure, which will receive government funding, will be built along provincial road 297. The cost of constructing the second stage of the Bolesławiec bypass (from the roundabout in Kruszyn to Kościuszki Street) will exceed PLN 64.6 million. The government will fund 60% of the construction, providing PLN 38.7 million. This amount will be spread over five years:

  • 2022: PLN 500,000
  • 2023: PLN 500,000
  • 2024: PLN 6,000,000
  • 2025: PLN 15,000,000
  • 2026: PLN 16,781,283.32

The construction of the bypass will relieve road traffic and improve residents’ safety. North–south traffic from the city centre will be redirected to the newly constructed bypass.

Details on the website: gov.pl/web/premier/rzad-dofinansuje-budowe-51-obwodnic-w-calym-kraju