We began September with construction work related to the expansion of the sports and recreation complex in the village of Bolesławice. The general contractor for the project is Place Zabaw „darmar” Dariusz Stos from Bożejowice. The cost of the work is PLN 433,575.

And he adds:

The area covered by the investment is located next to the Dom Ludowy building. The site has already been partially developed. So far, a games and play area has been created there, with tables for chess, table football, table tennis and Chinese checkers installed, as well as a recreational gazebo.

The work that has begun is the next stage in creating the sports and recreation complex; as part of the second stage, the following will be completed:

  • concrete slab paths enabling movement between the sports and recreation areas;
  • a playground with safe polyurethane and sand surfaces, featuring climbing equipment, trampolines, swings and a street workout area;
  • small architecture elements, including benches, waste bins and bicycle racks.

The planned completion date for the project is December 2021.

Moreover, work related to the construction of a wooden gazebo and the paving of the area with blocks has been completed in the village of Krępnica.

Work related to paving the area with blocks has also been completed in Parkoszów. A shelter measuring 5 m by 7 m will be built there. The newly created meeting place will soon be enhanced by purchased plantings of trees, shrubs and low-growing bushes.

The Bolesławiec municipality is carrying out the project “Purchase and installation of playground equipment and outdoor gyms in the Bolesławiec municipality”. Outdoor gym equipment will be installed in Bożejowice, Brzeźnik and Nowa, while playgrounds in the villages of Łąka and Trzebień will be supplemented with educational boards and a play set. Safe polyurethane surfacing has been installed beneath most of the equipment.

Other projects improving the appearance of localities and the safety of children and residents, completed recently in the municipality, include:

  • construction of a pavement next to the School and Preschool Complex in Bożejowice,
  • installation of a fence around the existing playground in the village of Kraśnik Dolny,
  • construction and installation of a bench-table in the village of Łaziska, together with paving the area beneath it,
  • construction and installation of an information board with a historical outline of the village of Nowe Jaroszowice,
  • paving the area with blocks and fencing the green area in the village of Suszki.