The Gromadka Municipality is carrying out the largest of this year's investment projects: the construction of a sanitary sewage network in Krzyżowa.

Municipal government:

At a cost of PLN 7,191,478.23, more than 15 km of gravity and pressure sanitary sewage networks will be constructed, along with connections to residential buildings and four sewage pumping stations. As part of the project, the contractor, Kanwod from Golina, will also modernize the water treatment plant in Krzyżowa, including the installation of a photovoltaic system supplying the water treatment plant and the largest sewage pumping station, as well as thoroughly restore the road surfaces affected by the construction work.

The first partial acceptance of the works is scheduled for mid-December this year, while all work should be completed in October 2021.