This is currently one of the most critical and busiest sections in Bolesławiec. The roadway is too narrow, and traffic jams often form. Drivers have difficulty turning right (from Grunwaldzka Street onto Tamka Street).
The work will be carried out by the Municipal Communal Services Department. Four tenders were announced. However, either no bids were submitted or they significantly exceeded the amounts planned in the budget for this investment.
What work will be carried out?
The pavement will be removed along its entire length, while the roadway will be levelled, reinforced and covered with new asphalt.
After the renovation, the roadway will be wider; an additional traffic lane is planned for vehicles turning from Sądowa Street towards the intersection. The traffic lights will be reconstructed. In addition, MZGK will build a pathway in the park and a new entrance to the court’s rear facilities.
The work is scheduled to be completed in May this year. Drivers should prepare for traffic disruptions. County:
The Bolesławiec County Governor asks for your understanding.