We reported that the reconstruction of the Solidarności Roundabout located between Bolesławiec and Kruszyn would begin on Tuesday. As Jacek Ogórek from the Lower Silesian Roads and Railways Service informed us, there will be no major disruptions during the first stage. Only temporary bus stops will be introduced.

In the initial phase, the work will be carried out outside the existing roundabout. DSDIK wants to complete as many works as possible outside it, so that the work during the second and third stages of the project—in which alternating traffic will be introduced—lasts as briefly as possible and, consequently, is as little disruptive to drivers as possible.

We will return to this topic.