Further investments in our city have been completed. A road with lighting and drainage has been built on Agatowa Street. The contractor is a company from nearby Brzeźnik, Bolesławiec County. The value of the project was nearly PLN 169,000.
The facilities at al. Wojska Polskiego have also been redeveloped. A new playground and kometka and volleyball courts have been created there. New pavements, internal roads, driveways and parking lots have also been built. Shrubs were planted, and benches and litter bins were installed. The value of the project was nearly PLN 592,000. The work was carried out by a company from Bolesławiec.
Meanwhile, work on the construction of a combined sewer network on Jaśminowa Street has been completed. The contractor for the investment was Przedsiębiorstwo Wodociągów i Kanalizacji w Bolesławcu. The total value of the project was nearly PLN 65,000. Moreover, using its own funds, PWiK built a water supply network more than 300 metres long. The cost of this investment was approximately PLN 90,000.
(information: Agnieszka Gergont/ii)