As reported by Bolesławiec City Hall:
Work has begun on the construction of a sidewalk along provincial road no. 297 on Kościuszki Street in Bolesławiec and in Łąka. The investor is the Lower Silesian Roads and Railways Service in Wrocław.
It also adds:
The new pedestrian route completes the missing section between Bolesławiec and Łąka. The section begins at the entrance to the “IBF” production facility and ends at the pedestrian crossing, connecting to the existing sidewalk on the right-hand side.
The sidewalk, located behind a drainage ditch, will have an asphalt surface. It will be 934.67 m long and 2 m wide.
The cost of the project is PLN 1,420,926, of which Bolesławiec City Hall contributed PLN 430,231.