In the material Will the investor manage to build the pools in a month? See the photos we wondered whether the City of Bolesławiec and the contractor would manage to meet the June opening deadline for the new water park on Spacerowa Street in Bolesławiec.
It is now known that this deadline will not be met. Why? As we have managed to establish, there are currently no conditions for connecting the facility to the power grid operated by Tauron. The resulting delay is expected to last about two months, which means that the park itself will not open during this year's summer season.
The consequence of this situation—for it is difficult to imagine such a park operating in autumn or winter—may be that the residents of Bolesławiec will only be able to enjoy the new attraction in the City of Ceramics... next summer.