On Friday, 19 January, a commission appointed by the Gromadka Municipality Head—with the assistance of OSP firefighters—began the technical acceptance procedures arising from the implementation of the project “Reconstruction and extension of a former industrial building for the needs of the OSP Fire Station and Police Station in Gromadka”.

Municipal officials:

The commission visually assessed the completed works and reviewed the opinions and comments of the construction supervision inspectors. Acceptance procedures will continue on the 29th of this month., when the investment will be formally completed.

The project is being carried out by AS-BUD Plus of Brenna. Cost: PLN 6,423,247.00.