From April to May 2021, the Facility completed the following investments:

  1. Construction of a water supply network—a crossing beneath the road with the relocation of a hydrant—on Polna Street in Gromadka, over a total length of 200 m. Investment value: PLN 58,414.57 gross;
  2. Construction of a sanitary sewerage network on Spokojna Street in Gromadka, over a total length of 200 m. Investment cost: PLN 79,976.65 gross.

The contractor for the above-mentioned works was Przedsiębiorstwo Konserwacji Urządzeń Wodnych i Melioracyjnych „MELIOBUD” Sp. z o.o., based in Nowogrodziec.

The completed investments are intended to improve the quality of life of Gromadka Municipality residents. The construction of water supply and sewerage networks in locations where these networks previously did not exist will make it possible to connect several more buildings to the newly constructed utilities.