The project involves equipping the area located around Ptasia–Widok streets with a water supply network approximately 1,560 m long and a combined sewer network approximately 1,830 m long.

The project also includes removing conflicts with the electricity network.

The investment will be carried out by Karem from Głogów. The costs amount to PLN 2,223,909. The funds come from the budget of the City of Bolesławiec.

City officials:

The project is scheduled for completion by the end of June 2020.