Gromadka Municipality, as the investor for the project Reconstruction of municipal road 103548 D running from the LSSE Krzywa–Szczytnica motorway interchange to the junction with the Osła–Różyniec county road, began the next stage of work after completing construction work related to the road base. This stage involves laying a mineral-asphalt surface.
The work is being carried out on a section approximately 1,200 m long and includes laying three surface layers: a 7-cm base course, a 5-cm binder course and a 4-cm wearing course.
Work involving the installation of the new surface on this section will take about 10 days. Once it has been completed and the technical inspection carried out, this part of the road is planned to be opened to motor traffic. Further reconstruction of the access road to the A4 interchange will be carried out with detours designated within the former airport.
The project is being carried out by Eltor of Lubań. The project is co-financed by the government Programme for the Development of Municipal and County Road Infrastructure for 2016–2019.
Janusz Górny, Gromadka Municipality/ii