Milling of the surface of Wilcza Street in Zawidów has been completed. Previously, the contractor, Skanska from Warsaw, widened and cleared the verges. The next stage involves supplementing the road base, laying a mineral-bituminous surface along approximately 3 kilometres, adjusting manholes, laying a crushed-stone surface, and installing vertical and horizontal road markings.
The renovation will take approximately four months and will cost more than PLN 1.8 million.
The renovation of Wilcza Street in Zawidów is being carried out as part of the Multiannual Programme entitled “National Programme for the Reconstruction of Local Roads. Stage II: Safety – Accessibility – Development”.
More photos on the Zawidów municipal office website.