Drivers in Bolesławiec will have to wait a little longer for traffic to be restored from the Jerzy Szmajdziński Roundabout towards the city centre. The delay concerns a project involving the expansion of the transport network and the construction of a new bridge over the Bóbr River. According to the General Directorate for National Roads and Motorways, the schedule has been changed because of unforeseen ground conditions.

While the roadbed was being excavated, the contractor encountered soil contaminated with rubble and other waste. The contamination must be removed and the ground properly prepared, which requires additional time.

According to a letter signed by Jacek Mozalewski, deputy director of the Wrocław branch of the General Directorate for National Roads and Motorways for Road and Bridge Management, the current temporary traffic organization will remain in place until 30 November.

Gallery (3)

Construction of the roundabout near the Bóbr River in Bolesławiec
1 / 3 Construction of the roundabout near the Bóbr River in Bolesławiec · Photo author: Miasto Bolesławiec
Construction of the roundabout near the Bóbr River in Bolesławiec
2 / 3 Construction of the roundabout near the Bóbr River in Bolesławiec · Photo author: Miasto Bolesławiec
Construction of the roundabout near the Bóbr River in Bolesławiec
3 / 3 Construction of the roundabout near the Bóbr River in Bolesławiec · Photo author: Miasto Bolesławiec

This means that the entrance from Zgorzelecka Street will remain closed until that date. Drivers will have to use the designated detours to Bolesławiec city centre and towards Zgorzelec, routed along municipal streets and national road no. 94.

The General Directorate for National Roads and Motorways assures that it is taking steps to limit the duration of the difficulties. At the same time, it warns that further changes to traffic organization may occur during the next stages of the project. According to the road manager, however, they should be significantly less troublesome for residents and drivers.